Rationalisation of existing offices to provide new modern environment and to promote cross functional collaboration, support strong communications, attract talent, and enable creativity. Ultimately, the restack returned 50% of current demise to Landlord.
Key Project Features
- Enhanced wellbeing facilities with large breakout spaces for staff
- Two stage procurement process to obtain optimum programme delivery
- Reuse of maximum amount of existing services installations to minimise waste
- Works executed within occupied multi-tenanted building in the heart of a major business park
Core Five Added Value
- Fast-track programme delivered by utilising a two stage procurement process
- Detailed cost planning throughout design development enabled careful monitoring and management of costs at each stage
- Final account agreed at Practical Completion providing Client cost certainty