48-49 Pall Mall

London / QNB / Trehearne Architects / 44,445 sqft

The project comprises a new 9 storey development (one level basement, ground floor plus seven upper storeys) constructed within a conversation area on the prestigious Pall Mall.

Due to the complex nature of the site and neighbouring buildings, there were four different elements of façade in addition to two-party walls which were retained. The service strategy was vital within the constrained building. Early design team coordination and Client input into the coordination of the core enabled a 1:8/m2 occupation density and a BCO compliant office space.

Key Project Features

  • The building required part of the existing façade to be retained with the new build steel structure tied into this element.
  • The shell and core construction constituted a concrete raft foundation with a concrete box basement construction below ground floor and a steel frame with composite floor slabs above ground floor.

Core Five Added Value

  • Provisional sums clearly defined and procured within budget
  • Early procurement of demolition contract and novation to main Contractor
  • Overlap of demolition and groundworks achieved 6 week programme saving
  • Direct procurement of demolition allowed design and construction to continue concurrently to reduce period between VP and completion
  • Early procurement of demolition contract and novation to main Contractor
  • Works procured via a single stage D&B tender within cost plan
  • 99% of contract sum fixed during main contract tender
We use the title ‘partner’ to describe a director, consultant or senior employee of Core Five Consulting Limited.
© All rights reserved Core Five 2022. Website designed & developed by evokeu
  • Terms and Conditions
  • Privacy Policy